1. Home
  2. Practice tests
  3. Load calculations

Free, no sign-up

OECP Load Calculation Practice

Calculators are not allowed on OECP written exams. You get pencils and scratch paper, and the math still has to be right. These 14 questions drill the hand calculations: load weight, sling tension, center of gravity and parts of line. Every answer shows the working.

Rules of thumb used in these questions

  • Weight = volume x unit weight (steel is about 490 lb per cubic foot)
  • Steel plate is about 40 lb per square foot for each inch of thickness
  • Parts of line = load divided by line pull, rounded up
  • Sling tension = share of the load x load angle factor (1.414 at 45 degrees)
  • With an off-center load, the pick point nearer the center of gravity carries more
The math on OECP exams
CalculatorsNot allowed. Devices with input or memory are prohibited
Handed to youPencils and scratch paper. Mobile crane candidates also get load charts
Mobile crane writtenLoad chart calculations are one of the listed subjects
Signal Person Rigger writtenRigging calculations are 10% of the questions

Sources: OECP FAQ and OECP Signal Person Rigger Candidate Manual. Checked November 2026.

14 load calculations practice questions

Pick an answer to see if you are right and why. These are original practice questions from the Crane Exam Prep question bank, not actual OECP exam questions.

  1. Load Calculation

    1. A stone concrete block measures 3 ft x 3 ft x 2 ft. What is its approximate weight?

    Show answer

    Answer: A. About 2,600 lbs. Volume = 3 x 3 x 2 = 18 cu ft. Weight = 18 x 144 = 2,592 lb, roughly 2,600 lb.

  2. Mobile Crane Essentials

    2. For a 1-inch rotation resistant rope, over what length would you check for 2 random broken wires?

    Show answer

    Answer: D. 6 inches (6 rope diameters). 6 diameters of a 1-inch rope is 6 inches; the criteria is 2 random broken wires in 6 rope diameters (or 4 in 30 diameters = 30 inches).

  3. Technical Knowledge

    3. A wire rope has a minimum breaking strength of 35,000 lb and a design factor of 3.5. What is its permissible line pull?

    Show answer

    Answer: C. 10,000 lb. Permissible line pull equals minimum breaking strength divided by the design factor: 35,000 ÷ 3.5 = 10,000 lb.

  4. Load Calculation

    4. An object weighs 150 lbs. per cubic foot and measures 4 ft X 3 ft X 3 ft, what does it weigh?

    Show answer

    Answer: D. 5,400 lbs. The volume is 4 x 3 x 3 = 36 cubic feet; at 150 lbs per cubic foot, 36 x 150 = 5,400 lbs.

  5. Load Calculation

    5. A 10,000 lb beam hangs from two pick points. The centre of gravity sits 8 ft from pick point 1 and 2 ft from pick point 2. What load does the sling at pick point 2 carry?

    Show answer

    Answer: D. 8,000 lb. Each sling's share is the load multiplied by the OPPOSITE distance over the total: sling 2 = 10,000 x 8 / (8+2) = 8,000 lb, and sling 1 = 10,000 x 2 / (8+2) = 2,000 lb. The sling closest to the centre of gravity carries the greatest share.

  6. Load Calculation

    6. A 6,000 lb load hangs from two sling legs, evenly shared, at a 45 degree angle of loading. What tension is in each leg?

    Show answer

    Answer: A. 4,242 lb. Each leg's vertical share is 6,000 / 2 = 3,000 lb. Multiply by the 45 degree load angle factor of 1.414: 3,000 x 1.414 = 4,242 lb per leg.

  7. Load Calculation

    7. A non-symmetrical load has section 1 weighing 10,000 lbs (CG1) and section 2 weighing 20,000 lbs (CG2), with CG1 and CG2 13.2 ft apart. Where is the combined center of gravity?

    Show answer

    Answer: C. 8.8 ft from CG1, along the line joining CG1 and CG2 (20,000/30,000 = 66.7% of 13.2 ft). Divide the weight of section 2 by the combined weight: 20,000/30,000 = 66.7%. The combined CG lies on the line joining CG1 and CG2 at 66.7% of 13.2 ft = 8.8 ft from CG1 — closer to the heavier section. The hook is positioned directly above this combined CG.

  8. Load Calculation

    8. A steel plate measures 8 ft by 4 ft and is 1 inch thick. Using the 40 lb/sq ft per inch rule, what is its approximate weight?

    Show answer

    Answer: A. 1,280 lbs. Area = 8 x 4 = 32 sq ft. At 40 lb per sq ft per inch of thickness: 32 x 40 x 1 = 1,280 lb.

  9. Load Calculation

    9. Steel plate weighs 40 lbs. per square foot. What is the approximate weight of a steel plate 8 ft long, 5 ft wide and 1 inch thick?

    Show answer

    Answer: D. 1,600 lbs. The plate's area is 8 x 5 = 40 square feet; at 40 lbs per square foot (per inch of thickness), 40 x 40 = 1,600 lbs.

  10. Load Calculation

    10. An object to be lifted is rectangular in shape and measures 5 ft long X 3 ft wide X 2 ft high. The volume of this object is?

    Show answer

    Answer: B. 30 cubic feet. Volume = length x width x height = 5 x 3 x 2 = 30, and volume is expressed in cubic feet.

  11. Load Calculation

    11. Allowable line pull is 12,000 lb per part. To lift a 40,000-lb load, the minimum parts of line required is:

    Show answer

    Answer: A. 4 parts. 40,000 / 12,000 = 3.33; you cannot reeve a fraction of a part, so round up to 4 parts of line.

  12. Load Calculation

    12. A solid steel shaft is 2 ft in diameter and 10 ft long. What is its approximate weight?

    Show answer

    Answer: A. About 15,400 lbs. Volume = 3.14 x (2 x 2)/4 x 10 = 31.4 cu ft. Weight = 31.4 x 490 = 15,386 lb, about 15,400 lb.

  13. Load Calculation

    13. What is the rule-of-thumb safe working load in tons for a 6x19 or 6x37 IPS IWRC wire rope sling with Flemish eye mechanical splice?

    Show answer

    Answer: D. Diameter squared times 8. Safe load in tons = rope diameter squared x 8. Examples: 1 in rope = 1 x 1 x 8 = 8 tons; 1/2 in rope = 0.5 x 0.5 x 8 = 2 tons. Rules of thumb are for single-leg use, new rigging in good condition, ignoring sling angle, D/d, and hitch type.

  14. Load Calculation

    14. You need to hoist a 45,000-lb load and the rope allows 12,920 lbs per part. Minimum parts of line?

    Show answer

    Answer: B. 4. 45,000 ÷ 12,920 = 3.48; three parts (38,760) is short, so four parts (51,680) are required.

FAQ

Common questions

Can I bring a calculator to the OECP written exam?
No. OECP prohibits calculators and other devices with input or memory. Pencils and scratch paper are provided.
How do I get faster at load math without a calculator?
Write every step down, round unit weights the way the trade does (490 for steel, 150 for concrete), and check the answer against the choices before you move on. Speed comes from repetition.
Are these the real OECP exam questions?
No. OECP does not release its questions and does not supply study material. These are original practice questions written from the OSHA crane rules and ASME B30 standards. This site is not affiliated with OECP or the IUOE.

More OECP practice tests

Keep studying in the full app.

5,000+ questions, lessons and a readiness score. Free to start.

Create a free account
More load calculations questionsFree account, no card
Open the app