25 questions
OECP practice test
The mixed mobile crane test.
Take the 25-question testFree, no sign-up
The OECP mobile crane written is one exam for three crane types: boom truck, lattice boom and telescopic boom. It has 75 multiple-choice questions, a two-hour limit and no calculators. Work through 20 free questions below and check each answer as you go.
Passing the mobile crane written opens the practical for any of the three mobile types. OECP sorts telescopic boom cranes by size: small is under 22 tons (boom trucks are their own type), medium is 22 to 75 tons, and large is over 75 tons. You take a separate practical for each crane type you want on your card.
| Questions | 75 multiple choice |
|---|---|
| Time limit | 2 hours |
| Passing score | Scaled score of 500 on a 200 to 800 scale |
| Crane types covered | Boom truck, lattice boom and telescopic boom |
| Calculators | Not allowed |
| Handed to you | Test booklet, load charts, pencils and scratch paper |
| Results | Pass or fail on the spot for computer-based tests. Paper tests are mailed within 10 working days |
| After you pass | A hands-on practical exam for each crane type |
Sources: OECP Crane Operator Candidate Manual and OECP FAQ. Checked November 2026.
Pick an answer to see if you are right and why. These are original practice questions from the Crane Exam Prep question bank, not actual OECP exam questions.
Answer: D. Raise the load a few inches off the ground and hold it. Hoist brakes are checked by raising the load a few inches off the ground and holding it to verify the brake holds.
Answer: C. Use that shorter-span chart, treated as manufacturer permission. If equal positioning is impossible, consult the manufacturer; a supplied shortest-span chart (e.g., the 50% chart) may be used as manufacturer permission.
Answer: A. personnel. OSHA prohibits carrying loads over people; a dropped load over personnel is the most serious crane hazard, so loads must be routed around workers.
Answer: B. They carry 3-phase current. AC transmission lines carry 3-phase current, which is why their conductors are arranged in threes.
Answer: C. Category II. The LMI/RCL is a Category II operational aid — 30-day repair window. Trap: it is not Category I like the anti-two-block, and not a 'safety device' like the horn.
Answer: D. A qualified person. 1926.1406(b) requires employer A/D procedures to be developed by a qualified person, and they must prevent unintended dangerous movement and collapse.
Answer: C. 20 ft (6.1 m). Table 5-3.4.5.1-1 specifies 20 ft (6.1 m) for over 200 kV to 350 kV; over 350 to 500 kV requires 25 ft, over 500 to 750 kV requires 35 ft, and over 750 to 1,000 kV requires 45 ft.
Answer: D. Days, months, and actual operating hours. Unlike OSHA's calendar-based scheme, manufacturers set intervals by days, months, and actual operating hours.
Answer: C. the boom may not be positioned even with nothing on the hook. Beyond the no-load stability limit, positioning the boom plus load-handling equipment is prohibited because the crane can overturn without any load.
Answer: A. Up to 30 percent or more, with extreme impact reaching 100 percent or more. Impact converts the load's momentum into extra force on the boom and ropes. Ordinary jerking commonly adds 30 percent or more; severe snatching or a sudden release can double the effective load.
Answer: A. 2. The minimum wraps allowed on a hoist drum is 2 unless the manufacturer specifies more.
Answer: A. Marshes and wetlands. The requirement that the ground be drained does not apply to marshes and wetlands, where marsh buggies or similar supports are used.
Answer: D. A lockable safety latch. Man basket service requires a hook with a lockable safety latch so the connection cannot accidentally release.
Answer: B. By the utility owner/operator, with the line visibly grounded at the worksite. Option 1 requires confirmation from the utility owner/operator that the line is deenergized and visibly grounded at the worksite.
Answer: D. The rated capacity is independent of the boom length. The boom length indicator requirement is waived where rated capacity does not depend on boom length.
Answer: C. As permitted by the manufacturer. 1926.1417(r) prohibits lifting loads over the front area of wheel-mounted equipment except as permitted by the manufacturer.
Answer: C. Frequent inspection. Maladjusted mechanisms and air/hydraulic leakage are frequent-inspection items under 1910.180(d)(2).
Answer: B. 60 degrees or higher. The preferred sling angle is 60 degrees or higher; lower angles put more stress on the sling.
Answer: C. 1% (about 0.57 degrees). The pre-shift check requires the crane to be within 1%, or roughly 0.57 degrees, of level before each shift and after each move.
Answer: C. Bring the lever back to neutral and then apply the swing brake and lock. Driving the swing in reverse to stop it slams the swing drive and whips the load, side loading the boom. The lever is returned to neutral, motion is allowed to settle, then the mechanical brake and positive lock are set.
Your result
FAQ
25 questions
The mixed mobile crane test.
Take the 25-question test75 questions
Its own written exam, including self-erecting tower cranes.
Tower crane practice test75 questions
Its own written exam for overhead crane operators.
Overhead crane practice test110 questions
One OECP certification for signaling and rigging together.
Signal person rigger practice test5,000+ questions, lessons and a readiness score. Free to start.