Tower crane operators take their own OECP written exam: 75 multiple-choice questions in two hours. To be eligible, 500 of your 1,000 documented hours must be on tower cranes. Try 20 free tower crane questions below.

What these practice questions cover

  • Erection, climbing and dismantling
  • Operation and wind limits
  • Ropes, hooks and sheaves
  • Limit devices and safety equipment
  • Inspections
  • ASME B30.3 and OSHA 1926.1435
OECP tower crane written exam at a glance
Questions75 multiple choice
Time limit2 hours
Passing scoreScaled score of 500 on a 200 to 800 scale
Crane types coveredTower cranes, including portable and self-erecting types
Experience needed1,000 documented hours in the past five years, 500 of them on tower cranes
CalculatorsNot allowed
After you passA hands-on tower crane practical exam

Sources: OECP Crane Operator Candidate Manual, OECP initial certification eligibility and OECP FAQ. Checked November 2026.

20 tower crane practice questions

Pick an answer to see if you are right and why. These are original practice questions from the Crane Exam Prep question bank, not actual OECP exam questions.

  1. Tower Crane

    1. When may an operator perform gear shifting on the hoist of a tower crane?

    Show answer

    Answer: B. Only with the hoist gear at a standstill. The operating instructions require gear shifting to be performed only with the hoist gear stopped.

  2. Tower — Erection & Structure

    2. For freestanding, braced, or guyed cranes, 'climbing' is best defined as the process by which the tower height is increased by what means?

    Show answer

    Answer: D. Adding tower sections at the top. Climbing increases height by adding tower sections at the top; internal climbing cranes are instead raised within the structure.

  3. Tower — Operations

    3. According to ASME B30.3, tower cranes shall not be operated when wind speeds exceed:

    Show answer

    Answer: D. The maximum velocity recommended by the manufacturer. Cranes shall not be operated when wind speeds exceed the maximum velocity recommended by the manufacturer.

  4. Tower Crane Test

    4. According to ASME B30.3, who should be present when telescoping or climbing operations begin?

    Show answer

    Answer: D. Operator. ASME B30.3 3-3.1.3(n): the operator must be present during climbing/telescoping.

  5. Tower Crane

    5. According to ASME B30.3, which cranes fall within its scope?

    Show answer

    Answer: B. Construction tower cranes and permanently mounted tower cranes. B30.3 applies to construction tower cranes and permanently mounted tower cranes powered by electric motors or internal combustion engines; self-erectors (B30.29) and mobile crane tower attachments (B30.5) are excluded.

  6. Tower — Erection & Structure

    6. Per ASME B30.3, high-strength (traction) bolts connecting mast sections should not be tensioned to full pre-stress until when?

    Show answer

    Answer: D. The crane is completely erected. Bolts should not be tensioned to provide full pre-stress until the crane is completely erected (3-1.1.2(e)).

  7. Tower — Operations

    7. Tower crane jib stops are required to be of what type?

    Show answer

    Answer: B. Shock absorbing, with a jib hoist limit switch also required on luffing cranes. Shock-absorbing stops keep the jib from slamming, and on luffing machines a jib hoist limit switch stops the jib before it reaches the stop at all.

  8. Tower — Ropes & Hooks

    8. Why must a tower crane operator never allow the hook block to be lowered so far that the hoist line goes slack at the drum?

    Show answer

    Answer: A. Slack rope can spool loosely or incorrectly onto the drum. If the block is lowered to the ground the hoist line must not be allowed to go slack, because slack rope spools loosely or incorrectly onto the drum.

  9. Tower Crane Test

    9. According to ASME B30.3, a class ___ fire extinguisher shall be kept in the cab or on the machinery platform:

    Show answer

    Answer: A. 10 ABC. ASME B30.3 3-1.23.4: a class 10 ABC fire extinguisher in the cab/machinery platform.

  10. Tower Crane

    10. A tower crane rated at its maximum load in 1-part line operation switches to 2-part operation. Its maximum rated load…

    Show answer

    Answer: B. Roughly doubles. Going from 1-part to 2-part reeving roughly doubles the maximum rated load, though it halves line speed.

  11. Tower — Operations

    11. At what overload does a tower crane's hoist line overload switch cut hoisting power?

    Show answer

    Answer: A. At a 5% overload, regardless of the jib or trolley position. The hoist line overload switch cuts hoisting power at a 5% overload no matter where the jib or trolley is positioned.

  12. Tower Crane Test

    12. According to ASME B30.3, what is the design factor for rotation resistant load hoist wire rope?

    Show answer

    Answer: C. 5.0 to 1. ASME B30.3 3-1.10.5(b): rotation resistant load hoist wire rope design factor = 5.0 to 1.

  13. Tower Crane

    13. Which tower crane mounting generally handles a load better while the crane is traveling?

    Show answer

    Answer: B. Rail mounted. Rail-mounted tower cranes run on engineered track and can accept any tower or jib configuration, so they travel under load better than a comparable mobile tower crane.

  14. Tower — Erection & Structure

    14. Before operating a tied-in tower crane at its maximum tower height, what must be done with the hydraulic top climbing unit?

    Show answer

    Answer: D. Lower it to the uppermost tie-in assembly. The manufacturer requires the top climbing unit to be lowered to the uppermost tie-in before the crane operates at its maximum tower configuration.

  15. Tower — Operations

    15. Tower crane overload switches are typically set to trip at a 5% overload. Why must you NOT load-test a tower crane the way many other cranes are tested?

    Show answer

    Answer: B. Because a tower crane must not be tested at more than 5% overload, unlike the 125% used for many crane types. Many crane types are proof-tested at 125% of rated capacity, but a tower crane must not be tested at more than a 5% overload.

  16. Tower — Ropes & Hooks

    16. Under ASME B30.3, the pitch diameters of the load block sheaves shall be not less than how many times the nominal rope diameter?

    Show answer

    Answer: D. 18 times. Load block sheave pitch diameters shall be not less than 18 times the nominal rope diameter; luffing boom hoist sheaves not less than 15 times.

  17. Tower Crane

    17. Where must the wind velocity (anemometer) device be mounted on a tower crane?

    Show answer

    Answer: C. At or near the top of the crane. A wind velocity measuring device shall be mounted at or near the top of the crane, with a readout in the cab.

  18. Tower Crane

    18. Why must concrete footings or crane mats be placed under the outrigger float pads of a self-erecting tower crane?

    Show answer

    Answer: A. The float pads alone are too small to spread reaction loads and prevent settlement. Outrigger reactions are substantial, and the float pads lack the area to spread them, so a qualified person sizes footings or mats using the soil report and the maximum reactions from the manufacturer.

  19. Tower — Erection & Structure

    19. Under ASME B30.3, proof of strength and stability of load-bearing tower crane structures shall be calculated per which standard?

    Show answer

    Answer: C. EN 14439, Section 5.2. B30.3 requires strength and stability of load-bearing structures to be calculated in accordance with EN 14439:2006+A2, Section 5.2.

  20. Tower — Operations

    20. In tower crane operation, what is "trolleying"?

    Show answer

    Answer: A. Moving the trolley in or out along the jib to change the load radius. Trolleying is the radius-change motion on a hammerhead crane, moving the trolley along the horizontal jib.

FAQ

Common questions

How many questions are on the OECP tower crane written exam?
It has 75 multiple-choice questions and a two-hour time limit. Scores are reported on a 200 to 800 scale and 500 passes.
How many tower crane hours do I need?
OECP requires 1,000 documented hours of crane-related experience or training in the past five years. For tower cranes, 500 of those hours must be tower crane hours.
Are self-erecting tower cranes included?
Yes. OECP lists the tower crane type as including portable and self-erecting cranes.
Are these the real OECP exam questions?
No. OECP does not release its questions and does not supply study material. These are original practice questions written from the OSHA crane rules and ASME B30 standards. This site is not affiliated with OECP or the IUOE.

More OECP practice tests

Keep studying in the full app.

5,000+ questions, lessons and a readiness score. Free to start.

Create a free account
More tower crane questionsFree account, no card
Open the app