OECP combines signaling and rigging in one certification. The written exam has 110 multiple-choice questions in two hours, and 40% of it is signaling. The 20 free questions below follow the same split: 8 on signals and 12 on rigging.

What these practice questions cover

  • Standard hand, voice and audible signals
  • Signal person qualification under OSHA 1926.1428
  • Sling types, hitches and removal criteria
  • Shackles, hooks and rigging hardware
  • Center of gravity and load control
  • ASME B30.9 and B30.26
OECP Signal Person Rigger written exam at a glance
Questions110 multiple choice
Time limit2 hours
Passing scoreScaled score of 500 on a 200 to 800 scale
Rigging standards20% of the questions
Rigging operations30% of the questions
Rigging calculations10% of the questions
Signaling40% of the questions
Practical examFour tests: hand signals, radio signals, rigging inspection and a rigging practical
Experience needed500 hours of experience or training in Operating Engineer work in the past five years, plus a certificate from an IUOE-recognized signal person rigging training program
Card life5 years

Source: OECP Signal Person Rigger Candidate Manual (2025 edition). Checked November 2026.

20 signal person rigger practice questions

Pick an answer to see if you are right and why. These are original practice questions from the Crane Exam Prep question bank, not actual OECP exam questions.

  1. Signals

    1. The hand signal DOG EVERYTHING means:

    Show answer

    Answer: C. Pause and hold — the operator stops all crane motions and holds the load and machine functions where they are. DOG EVERYTHING (hands clasped in front of the body) tells the operator to suspend all functions and hold everything in place until further signals are given.

  2. Signals

    2. The signal person should be positioned so that they can…

    Show answer

    Answer: C. See the load and point of operation and be clearly seen by the operator. The signal person must keep a clear view of the load/point of operation and stay visible to the operator; standing under the load is prohibited.

  3. OSHA 1926 Subpart CC

    3. According to OSHA 1926.1420, when signals are transmitted by radio, the operator's reception of signals must be by:

    Show answer

    Answer: C. A hands-free system. 1926.1420(c) requires the operator's reception of signals to be by a hands-free system, and devices must be tested on site before operations begin.

  4. ASME B30.5 (Mobile Cranes)

    4. According to ASME B30.5, the audible travel signal for BACK UP is:

    Show answer

    Answer: B. Three short audible signals. Para 5-3.3.7 specifies STOP: one short signal; GO AHEAD: two short signals; BACK UP: three short signals.

  5. General Knowledge

    5. When using voice signals, what element is given first?

    Show answer

    Answer: D. Function and direction. Voice signals are given in the order: function and direction first, then distance/speed, then function stop.

  6. OSHA 1926 Subpart CC

    6. According to OSHA 1926.1422, hand signal charts must be:

    Show answer

    Answer: B. Posted on the equipment or conspicuously posted in the vicinity of the hoisting operations. 1926.1422 requires hand signal charts to be either posted on the equipment or conspicuously posted in the vicinity of hoisting operations.

  7. OSHA 1926 Subpart CC

    7. According to OSHA 1926.1419, when using hand signals, which method must be used?

    Show answer

    Answer: D. The Standard Method in Appendix A of Subpart CC, unless infeasible or the operation is not covered by it. 1926.1419(c)(1) requires the Standard Method (Appendix A) for hand signals; non-standard signals may be used only where the Standard Method is infeasible or does not cover the operation, with prior agreement among signal person, operator, and lift director.

  8. OSHA 1926 Subpart CC

    8. According to OSHA 1926.1420, radio signal transmission must be through a dedicated channel, except:

    Show answer

    Answer: C. Multiple cranes and one or more signal persons may share a dedicated channel to coordinate operations, or when coordinating with trains near railroad tracks. 1926.1420(b) requires a dedicated channel except for coordinating multiple cranes/signal persons or coordinating with other equipment or trains on or adjacent to railroad tracks.

  9. Rigging

    9. An object placed in the eye of a WIRE ROPE sling must be no wider than…

    Show answer

    Answer: C. One-half the length of the eye. For wire rope slings, the object in the eye must not exceed half the eye length to avoid spreading and damaging the eye.

  10. Rigging Hardware

    10. Why must the load be centered in the base (bowl or saddle) of a hook?

    Show answer

    Answer: D. To prevent point loading of the hook. Centering the load in the hook's bowl prevents point loading, which can overload and deform the hook.

  11. Rigging 1

    11. What does OSHA say about repaired or reconditioned natural or synthetic fiber rope slings?

    Show answer

    Answer: A. Their use is prohibited — only slings made from new rope may be used. Only fiber rope slings made from new rope may be used; repaired or reconditioned fiber rope slings are prohibited.

  12. ASME B30.9 (Slings)

    12. A chain link is embossed only with the letter "A". What does this tell you?

    Show answer

    Answer: C. The chain is alloy, but not necessarily suitable for overhead lifting. "A" means alloy only; without an accompanying 8 the chain is likely a lower grade (usually grade 6) and not suitable for overhead lifting.

  13. Rigging

    13. In rigging, the "design factor" (safety factor) is defined as:

    Show answer

    Answer: B. The ratio of a component's minimum breaking strength to its working load limit. Design factor = minimum breaking strength ÷ WLL. For example, most slings use a 5:1 design factor, so a sling with 25,000 lb breaking strength has a 5,000 lb WLL.

  14. Rigging 1

    14. An eye splice in a synthetic fiber rope sling must consist of at least how many full tucks?

    Show answer

    Answer: D. Four. Synthetic fiber rope eye splices require at least four full tucks (manila requires three); short splices require eight and six full tucks respectively.

  15. ASME B30.9 (Slings)

    15. A web sling is found with a knot tied in its body. Under OSHA/ASME criteria the sling must be

    Show answer

    Answer: B. removed from service. Knots in any part of the sling are a listed removal criterion for synthetic webbing slings, along with burns, melting, cuts, broken stitching, and chemical or UV damage.

  16. Rigging

    16. Approximately what strength efficiency remains in a fiber rope with a hitch, and with an eye or short splice?

    Show answer

    Answer: B. About 75 percent for a hitch and about 85 percent for a splice. Straight rope is 100 percent. A splice costs about 15 percent, a hitch about 25 percent, and a knot or bend about 50 percent — always rate the system at its weakest point.

  17. Rigging 1

    17. A wire rope SLING is removed for 10 random broken wires in one rope lay. A running wire rope on the crane is removed for...

    Show answer

    Answer: B. 6 random broken wires in one lay, or 3 in one strand. Running rope removal is 6 randomly distributed broken wires in one lay or 3 in one strand; a wire rope sling uses 10 in one lay or 5 in one strand, so the criteria must not be confused.

  18. ASME B30.9 (Slings)

    18. According to ASME B30.9, what shall be done with cracked, broken, stretched, bent, or twisted chain links?

    Show answer

    Answer: C. They shall be replaced, not repaired. Para. 9-1.9.6(e): cracked, broken, stretched, bent, or twisted chain links shall not be repaired; they shall be replaced.

  19. Rigging

    19. The center of gravity of an object is best defined as:

    Show answer

    Answer: D. The point at which the object will balance, where the entire weight may be considered concentrated. The center of gravity is the balance point of the object; the entire weight may be considered as concentrated at this point.

  20. Rigging

    20. If the load does not balance properly after being raised, what step should be taken?

    Show answer

    Answer: C. lower the load to the ground. An unbalanced load must be set back down and the rigging adjusted; continuing the lift risks the load shifting or slipping out of the slings.

FAQ

Common questions

How many questions are on the OECP Signal Person Rigger written exam?
The written has 110 multiple-choice questions and a two-hour time limit. Scores are reported on a 200 to 800 scale and 500 passes.
Is it one certification or two?
One. OECP certifies signaling and rigging together as Signal Person Rigger.
What is on the Signal Person Rigger practical?
Four tests: hand signals, radio signals, a rigging inspection and a rigging practical with choker, double-wrap basket and vertical hitches.
How much of the written is signaling?
Signaling is 40% of the questions. Rigging operations is 30%, rigging standards 20% and rigging calculations 10%.
Are these the real OECP exam questions?
No. OECP does not release its questions and does not supply study material. These are original practice questions written from the OSHA crane rules and ASME B30 standards. This site is not affiliated with OECP or the IUOE.

More OECP practice tests

Keep studying in the full app.

5,000+ questions, lessons and a readiness score. Free to start.

Create a free account
More signal person rigger questionsFree account, no card
Open the app